You need to check availability for other enterprise resources with the same skills as your overallocated resources
You need to communicate this information to your project team and other project stakeholders who are not necessarily enterprise resources
You need to link Task A and Task B so that they occur in sequence, with the start date for Task B 5 days after the finish date for Task A