###BeginCaseStudy###
Testlet 1
General Overview
Contoso Ltd. is an international manufacturing company that has 30 000 users. Contoso has the following departments: sales, research, marketing, human
resources, executive, manufacturing, and legal. The sales department has 2.000 users. All of the
users in the sales department are located in the United States. The research department has 3.000 users. All of the users in the research department are located in
Europe.
Physical Locations
Contoso has two main offices. The offices are located in Houston and Frankfurt. Each office has 15.000 users. The offices connect to each other by using an MPLS
network. Each office connects directly to the Internet.
Existing Environment
Lync Server Infrastructure
Contoso has a Lync Server 2013 infrastructure that only uses internal instant messaging (IM) and presence. The infrastructure contains a single Enterprise Edition
Front End pool that services all of the users.
Contoso uses a SIP domain ofcontoso.com for all of the users. Client computers have either Microsoft Lync 2010 or Microsoft Lync 2013 installed. Before deploying
Skype for Business Server 2015 and migrating the users, you implement a small pilot project to test the functionality of Skype for Business Server 2015.
Problem Statements
The users in the pilot report that occasionally, they cannot sign in to Skype for Business 2015.
Requirements
Business goal
Contoso plans to upgrade to Skype for Business Server 2015 during the next six months. Contoso must deploy all of theconferencing and edge services. Contoso
must
also configure federation with its parent company, which is named Proseware Inc. Proseware is located in Europe and has a Lync Server 2010 infrastructure
Contoso must minimize hardware and software purchasingcosts. while guaranteeing performance levels for all Skype for Business Server 2015 workloads.
Planned Changes
Contoso plans to implement the following workloads in the Skype for Business Server 2015 deployment:
The FQDNs of the edge services will be configured as shown in the following table.
Technical Requirements
Contoso identifies the following technical requirements for the planned deployment:
Security Requirements
Contoso identifies the following security requirements for the planned deployment:
###EndCaseStudy###
Your company has a main office and a branch office. The main office is located in Amsterdam. The branch office is located in New York. Each office has a data
center. The offices connect to each other by using a high-bandwidth, low-latency wide area network (WAN) link. You have a Skype for Business Server 2015
infrastructure in both of the locations. The solution supports 5,000 users.
You plan to deploy a persistent chat infrastructure.
You need to ensure that persistent chat rooms remain available if a data center fails.
What should you do?
A.
Create one Persistent Chat Server pool that contains one active chat server and one standby chat server.
B.
Create one Persistent Chat Server pool that contains two active chat servers.
C.
Create two Persistent Chat Server pools that each contains one active chat server.
D.
Create two Persistent Chat Server pools that each contains one active chat server and one standby chat server.