Which one of the following is a valid risk response for a negative risk event

There are seven risk responses for any project. Which one of the following is a valid risk response
for a negative risk event

There are seven risk responses for any project. Which one of the following is a valid risk response
for a negative risk event

A.
Acceptance

B.
Enhance

C.
Share

D.
Exploit