Which of the following processes is described in the statement below?

Which of the following processes is described in the statement below? “It is the process of
implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new
risks, and evaluating risk process effectiveness throughout the project.”

Which of the following processes is described in the statement below? “It is the process of
implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new
risks, and evaluating risk process effectiveness throughout the project.”

A.
Monitor and Control Risks

B.
Identify Risks

C.
Perform Qualitative Risk Analysis

D.
Perform Quantitative Risk Analysis



Leave a Reply 0

Your email address will not be published. Required fields are marked *