Walter is the project manager of a large construction project. He’ll be working with several vendors
on the project. Vendors will be providing materials and labor for several parts of the project. Some
of the works in the project are very dangerous so Walter has implemented safety requirements for
all of the vendors and his own project team. Stakeholders for the project have added new
requirements, which have caused new risks in the project. A vendor has identified a new risk that
could affect the project if it comes into fruition. Walter agrees with the vendor and has updated the
risk register and created potential risk responses to mitigate the risk. What should Walter also
update in this scenario considering the risk event?
A.
Project contractual relationship with the vendor
B.
Project management plan
C.
Project communications plan
D.
Project scope statement