You are the project manager of the HJK Project for your organization. You and the project team
have created risk responses for many of the risk events in the project. Where should you
document the proposed responses and the current status of all identified risks?
A.
Risk management plan
B.
Lessons learned documentation
C.
Risk register
D.
Stakeholder management strategy