Part of your change management plan details what should happen in the change control system
for your project. Theresa, a junior project manager, asks what the configuration management
activities are for scope changes. You tell her that all of the following are valid configuration
management activities except for which one?
A.
Configuration Verification and Auditing
B.
Configuration Item Costing
C.
Configuration Identification
D.
Configuration Status Accounting