DRAG DROP
Your company has two offices. Each office is configured as an Active Directory site. The
sites are named Site1 and Site2. You have an Exchange Server 2013 organization that is
configured as shown in the following exhibit. (Click the Exhibit button.)
Datacenter Activation Coordination (DAC) mode is enabled on the database availability
group (DAG) named DAG1. You are testing a site failover by shutting down all of the servers
in Site1. You need to mount the databases in Site2. Which three commands should you run
in sequence? (To answer, move the appropriate three commands from the list of commands
to the answer area and arrange them in the correct order.)
The correct sequence is:
Stop-DatabaseAvailabilityGroup –ActiveDirectorySite:Site1
Stop-Service -Name CLUSSVC
Restore-DatabaseAvailabilityGroup –ActiveDirectorySite:Site2
Reference:
http://blogs.technet.com/b/timmcmic/archive/2013/02/03/part-4-datacenter-activation-coordination-and-the-prevention-of-split-brain.aspx