Which of the following would be a MAJOR consideration for an organization defining its business
continuity plan (BCP) or disaster recovery program (DRP)?
A.
Setting up a backup site
B.
Maintaining redundant systems
C.
Aligning with recovery time objectives (RTOs)
D.
Data backup frequency
Explanation:
BCP.’DRP should align with business RTOs. The RTO represents the amount of time allowed for
the recovery of a business function or resource after a disaster occurs. The RTO must be taken
into consideration when prioritizing systems for recovery efforts to ensure that those systems that
the business requires first are the ones that are recovered first.