which of the following is the PRIMARY concern?

When an organization is using an automated tool to manage and house its business continuity plans, which of
the following is the PRIMARY concern?

When an organization is using an automated tool to manage and house its business continuity plans, which of
the following is the PRIMARY concern?

A.
Ensuring accessibility should a disaster occur

B.
Versioning control as plans are modified

C.
Broken hyperlinks to resources stored elsewhere

D.
Tracking changes in personnel and plan assets

Explanation:

If all of the plans exist only in electronic form, this presents a serious weakness if the electronic version is dependent on restoration of the intranet or other systems that are no longer available. Versioning control and tracking changes in personnel and plan assets is actually easier with an automated system. Broken hyperlinks are a concern, but less serious than plan accessibility.



Leave a Reply 0

Your email address will not be published. Required fields are marked *