You work as the project manager for Bluewell Inc. Your project has several risks that will affect
several stakeholder requirements. Which project management plan will define who will be
available to share information on the project risks?
A.
Resource Management Plan
B.
Risk Management Plan
C.
Stakeholder management strategy
D.
Communications Management Plan
Explanation:
The Communications Management Plan defines, in regard to risk management, who will be
available to share information on risks and responses throughout the project.
The Communications Management Plan aims to define the communication necessities for the
project and how the information will be circulated. The Communications Management Plan setsthe communication structure for the project. This structure provides guidance forcommunication
throughout the project’s life and is updated as communication needs change. The Communication
Managements Plan identifies and defines the roles of persons concerned with the project. It
includes a matrix known as the communication matrix to map the communication requirements of
the project.
Answer C is incorrect. The stakeholder management strategy does not address risk
communications.
Answer B is incorrect. The Risk Management Plan defines risk identification, analysis, response,
and monitoring.
Answer A is incorrect. The Resource Management Plan does not define risk communications.