which one?

You are the project manager of GHT project. Your project team is in the process of identifying
project risks on your current project. The team has the option to use all of the following tools and
techniques to diagram some of these potential risks EXCEPT for which one?

You are the project manager of GHT project. Your project team is in the process of identifying
project risks on your current project. The team has the option to use all of the following tools and
techniques to diagram some of these potential risks EXCEPT for which one?

A.
Process flowchart

B.
Ishikawa diagram

C.
Influence diagram

D.
Decision tree diagram

Explanation:

Decision tree diagrams are used during the Quantitative risk analysis process and not in risk
identification.
All the these options are diagrammatical techniques used in the Identify risks process.



Leave a Reply 0

Your email address will not be published. Required fields are marked *