which of the following levels do this identified risk exists?

You are the project manager in your enterprise. You have identified risk that is noticeable failure
threatening the success of certain goals of your enterprise. In which of the following levels do this
identified risk exists?

You are the project manager in your enterprise. You have identified risk that is noticeable failure
threatening the success of certain goals of your enterprise. In which of the following levels do this
identified risk exists?

A.
Moderate risk

B.
High risk

C.
Extremely high risk

D.
Low risk

Explanation:

Moderate risks are noticeable failure threatening the success of certain goals.
Answer C is incorrect. Extremely high risk are the risks that has large impact on enterprise and
are most likely results in failure with severe consequences.
Answer B is incorrect. High risk is the significant failure impacting in certain goals not being met.
Answer D is incorrect. Low risks are the risk that results in certain unsuccessful goals.