You are an experienced Project Manager that has been entrusted with a project to develop a
machine which produces auto components. You have scheduled meetings with the project team
and the key stakeholders to identify the risks for your project. Which of the following is a key
output of this process?
A.
Risk Register
B.
Risk Management Plan
C.
Risk Breakdown Structure
D.
Risk Categories
Explanation:
The primary outputs from Identify Risks are the initial entries into the risk register. The risk register
ultimately contains the outcomes of other risk management processes as they are conducted,
resulting in an increase in the level and type of information contained in the risk register over time.
process, which happens prior to the starting of risk identification.