which of the following risk management capability maturity levels do the statement given below is true?

For which of the following risk management capability maturity levels do the statement given
below is true? “Real-time monitoring of risk events and control exceptions exists, as does
automation of policy management”

For which of the following risk management capability maturity levels do the statement given
below is true? “Real-time monitoring of risk events and control exceptions exists, as does
automation of policy management”

A.
Level 3

B.
Level 0

C.
Level 5

D.
Level 2

Explanation:

An enterprise’s risk management capability maturity level is 5 when real-time monitoring of risk
events and control exceptions exists, as does automation of policy management.
Answer B is incorrect. In level 0 of risk management capability maturity model, enterprise does

not recognize the importance of considering the risk management or the business impact from IT
risk.