Where are all risks and risk responses documented as the project progresses?

Where are all risks and risk responses documented as the project progresses?

Where are all risks and risk responses documented as the project progresses?

A.
Risk management plan

B.
Project management plan

C.
Risk response plan

D.
Risk register

Explanation:

All risks, their responses, and other characteristics are documented in the risk register. As the
project progresses and the conditions of the risk events change, the risk register should be
updated to reflect the risk conditions.
Answer A is incorrect. The risk management plan addresses the project management’s approach
to risk management, risk identification, analysis, response, and control.
Answer C is incorrect. The risk response plan only addresses the planned risk responses for the
identified risk events in the risk register.
Answer B is incorrect. The project management plan is the overarching plan for the project, not
the specifics of the risk responses and risk identification.