You are working with a vendor on your project. A stakeholder has requested a change for the
project, which will add value to the project deliverables. The vendor that you’re working with on the
project will be affected by the change. What system can help you introduce and execute the
stakeholder change request with the vendor?
A.
Contract change control system
B.
Scope change control system
C.
Cost change control system
D.
Schedule change control system
Explanation:
The contract change control system is part of the project’s change control system. It addresses
changes with the vendor that may affect the project contract. Change control system, a part of the
configuration management system, is a collection of formal documented procedures that define
how project deliverables and documentation will be controlled, changed, and approved.
Answer C is incorrect. The cost change control system manages changes to costs in the project.
Answer D is incorrect. There is no indication that the change could affect the project schedule.
Answer B is incorrect. The scope may change because of the stakeholder change request.
Vendor’srelationship to the project, hence this choice is not the best answer.