What are the requirements of monitoring risk?
Each correct answer represents a part of the solution. Choose three.
A.
Information of various stakeholders
B.
Preparation of detailed monitoring plan
C.
Identifying the risk to be monitored
D.
Defining the project’s scope
Explanation:
It is important to first understand the risk to be monitored, prepare a detailed plan and define the
project’s scope for monitoring risk. In the case of a monitoring project, this step should involve
process owners, data owners, system custodians and other process stakeholders.
Answer A is incorrect. Data regarding stakeholders of the project is not required in any phase of
risk monitoring.