Your project spans the entire organization. You would like to assess the risk of your project but
worried about that some of the managers involved in the project could affect the outcome of any
risk identification meeting. Your consideration is based on the fact that some employees would not
want to publicly identify risk events that could declare their supervision as poor. You would like a
method that would allow participants to anonymously identify risk events. What risk identification
method could you use?
A.
Delphi technique
B.
Root cause analysis
C.
Isolated pilot groups
D.
SWOT analysis
Explanation:
The Delphi technique uses rounds of anonymous surveys to build consensus on project risks.
Delphi is a technique to identify potential risk. In this technique, the responses are gathered via
aquestionand their inputs are organized according to their contents. The collected responses are
sent back to these experts for further input, addition, and comments. The final list of risks in the
project is prepared after that. The participants in this technique are anonymous and therefore it
helps prevent a person from unduly influencing the others in the group. The Delphi technique
helps in reaching the consensus quickly.
Answer C is incorrect. Isolated pilot groups is not a valid risk identification activity.
Answer B is incorrect. Root cause analysis is not an anonymous approach to risk identification.
Answer D is incorrect. SWOT analysis evaluates the strengths, weaknesses, opportunities, and
threats of the project.