What will be your NEXT step?

You are working as the project manager of the ABS project. The project is for establishing a
computer network in a school premises. During the project execution, the school management
asks to make the campus Wi-Fi enabled. You know that this may impact the project adversely.
You have discussed the change request with other stakeholders. What will be your NEXT step?

You are working as the project manager of the ABS project. The project is for establishing a
computer network in a school premises. During the project execution, the school management
asks to make the campus Wi-Fi enabled. You know that this may impact the project adversely.
You have discussed the change request with other stakeholders. What will be your NEXT step?

A.
Update project management plan.

B.
Issue a change request.

C.
Analyze the impact.

D.
Update risk management plan.

Explanation:

The first step after receiving any change request in a project must be first analyzed for its impact.
Changes may be requested by any stakeholder involved with the project. Although, they may be
initiated verbally, they should always be recorded in written form and entered into the change
management and/or configuration management.
request. Any change request must be followed by the impact analysis of the change.



Leave a Reply 0

Your email address will not be published. Required fields are marked *