Which of the following is an acceptable method for handling positive project risk?

Which of the following is an acceptable method for handling positive project risk?

Which of the following is an acceptable method for handling positive project risk?

A.
Exploit

B.
Avoid

C.
Mitigate

D.
Transfer

Explanation:

Exploit is a method for handling positive project risk.
not the positive risk.