What this resulting risk is known as?

You are the project manager of HGT project. You have identified project risks and applied
appropriate response for its mitigation. You noticed a risk generated as a result of applying

response. What this resulting risk is known as?

You are the project manager of HGT project. You have identified project risks and applied
appropriate response for its mitigation. You noticed a risk generated as a result of applying

response. What this resulting risk is known as?

A.
Pure risk

B.
Secondary risk

C.
Response risk

D.
High risk

Explanation:

Secondary risk is a risk that is generated as the result of risk response.
Answer A is incorrect. A pure risk is a risk that has only a negative effect on the project. Pure risks
are activities that are dangerous to complete and manage such as construction, electrical work, or
manufacturing.