Wendy is about to perform qualitative risk analysis on the identified risks within her project. Which
one of the following will NOT help Wendy to perform this project management activity?
A.
Risk management plan
B.
Project scope statement
C.
Risk register
D.
Stakeholder register
Explanation:
The stakeholder register is not an input to the qualitative risk analysis process. The four inputs are
the risk register, risk management plan, project scope statement, and organizational process
assets.
Answer C is incorrect. The risk register can help Wendy to perform qualitative risk analysis.
Answer B is incorrect. The project scope statement is needed to help with qualitative risk analysis.
Answer A is incorrect. The Risk management plan is an input to the risk qualitative analysis
process.