Which one of the following will NOT help you, the project manager, to prepare for risk monitoring and controlling?

There are four inputs to the Monitoring and Controlling Project Risks process. Which one of the
following will NOT help you, the project manager, to prepare for risk monitoring and controlling?

There are four inputs to the Monitoring and Controlling Project Risks process. Which one of the
following will NOT help you, the project manager, to prepare for risk monitoring and controlling?

A.
Risk register

B.
Work Performance Information

C.
Project management plan

D.
Change requests

Explanation:

Change requests are not one of the four inputs to the Risk Monitoring and Controlling Process.
The four inputs are the risk register, the project management plan, work performance information,
and performance reports.
Controlling Process.



Leave a Reply 0

Your email address will not be published. Required fields are marked *