What portion of the project will you most likely use for probability distributions?

Ned is the project manager of the HNN project for your company. Ned has asked you to help him
complete some probability distributions for his project. What portion of the project will you most
likely use for probability distributions?

Ned is the project manager of the HNN project for your company. Ned has asked you to help him
complete some probability distributions for his project. What portion of the project will you most
likely use for probability distributions?

A.
Bias towards risk in new resources

B.
Risk probability and impact matrixes

C.
Uncertainty in values such as duration of schedule activities

D.
Risk identification

Explanation:

Risk probability distributions are likely to be utilized in uncertain values, such as time and cost
estimates for a project.
Answer D is incorrect. Risk probability distributions are not likely the risk identification.
Answer B is incorrect. Risk probability distributions are not likely to be used with risk probability
and impact matrices.
Answer A is incorrect. Risk probability distributions do not typically interact with the bias towards
risks in new resources.