what is this term called?

When it appears that a project risk is going to happen, what is this term called?

When it appears that a project risk is going to happen, what is this term called?

A.
Issue

B.
Contingency response

C.
Trigger

D.
Threshold

Explanation:

A trigger is a warning sign or a condition that a risk event is likely to occur within the project.
Answer B is incorrect. A contingency response is a pre-planned response for a risk event, such as
a rollback plan.
Answer A is incorrect. Issues are events that come about as a result of risk events. Risks become
issues only after they have actually occurred.
Answer D is incorrect. A threshold is a limit that the risk passes to actually become an issue in the
project.