What should you do with these events that have not happened and would not happen now in the project?

You are the project manager of the AFD project for your company. You are working with the
project team to reassess existing risk events and to identify risk events that have not happened
and whose relevancy to the project has passed. What should you do with these events that have
not happened and would not happen now in the project?

You are the project manager of the AFD project for your company. You are working with the
project team to reassess existing risk events and to identify risk events that have not happened
and whose relevancy to the project has passed. What should you do with these events that have
not happened and would not happen now in the project?

A.
Add the risk to the issues log

B.
Close the outdated risks

C.
Add the risks to the risk register

D.
Add the risks to a low-priority watch-list

Explanation:

Risks that are now outdated should be closed by the project manager, there is no need to keep
record of that.

Answer D is incorrect. Risks with low probability and low impact go on the risk watchlist.
Answer C is incorrect. Identified risks are already in the risk register.
Answer A is incorrect. Risks do not go into the issue log, but the risk register.



Leave a Reply 0

Your email address will not be published. Required fields are marked *