What activity should be done for effective post-implementation reviews during the project?

What activity should be done for effective post-implementation reviews during the project?

What activity should be done for effective post-implementation reviews during the project?

A.
Establish the business measurements up front

B.
Allow a sufficient number of business cycles to be executed in the new system

C.
Identify the information collected during each stage of the project

D.
Identify the information to be reviewed

Explanation:

For effective post-implementation review the business measurements up front is established
during the project.
during each stage of project is done in pre-project phase and not during project for effective postimplementation review.
Answer B is incorrect. Executing sufficient number of business cycles in the new system is done
after the completion of the project.