Which project management plan will define who will be available to share information on the project risks?

You work as the project manager for Company Inc. The project on which you are working has
several risks that will affect several stakeholder requirements. Which project management plan will
define who will be available to share information on the project risks?

You work as the project manager for Company Inc. The project on which you are working has
several risks that will affect several stakeholder requirements. Which project management plan will
define who will be available to share information on the project risks?

A.
Resource Management Plan

B.
Communications Management Plan

C.
Risk Management Plan

D.
Stakeholder management strategy

Explanation:

The Communications Management Plan defines, in regard to risk management, who will be
available to share information on risks and responses throughout the project.
The Communications Management Plan aims to define the communication necessities for the
project and how the information will be circulated. The Communications Management Plan sets
the communication structure for the project. This structure provides guidance for communication
throughout the project’s life and is updated as communication needs change. The Communication
Managements Plan identifies and defines the roles of persons concerned with the project. It
includes a matrix known as the communication matrix to map the communication requirements of

the project.
Answer D is incorrect. The stakeholder management strategy does not address risk
communications.
Answer C is incorrect. The Risk Management Plan deals with risk identification, analysis,
response, and monitoring.
Answer A is incorrect. The Resource Management Plan does not define risk communications.