Where should you document the proposed responses and the current status of all identified risks?

You are the project manager of the HJK Project for your organization. You and the project team
have created risk responses for many of the risk events in the project. Where should you
document the proposed responses and the current status of all identified risks?

You are the project manager of the HJK Project for your organization. You and the project team
have created risk responses for many of the risk events in the project. Where should you
document the proposed responses and the current status of all identified risks?

A.
Stakeholder management strategy

B.
Lessons learned documentation

C.
Risk register

D.
Risk management plan

Explanation:

Risks and the corresponding responses are documented in the risk register for the project. Risk
register is a document that contains the results of the qualitative risk analysis, quantitative risk
analysis, and risk response planning. Description, category, cause, probability of occurring, impact
on objectives, proposed responses, owner, and the current status of all identified risks are put in
the risk register.
Answer B is incorrect. The outcome of risk events and the corresponding risk responses may be
documented in the project’s lessons learned documented, but the best answer is to document the
risk responses as part of the risk register.
Answer D is incorrect. The risk management plan defines how risks will be identified and
analyzed, the available responses, and the monitoring and controlling of the risk events. The
actual risk responses are included in the risk register.
Answer A is incorrect. The stakeholder management strategy defines how stakeholders and their
threats, perceived threats, opinions, and influence over the project objectives will be addressed
and managed.



Leave a Reply 0

Your email address will not be published. Required fields are marked *