You are the project manager for GHT project. You need to perform the Qualitative risk analysis
process. When you have completed this process, you will produce all of the following as part of the
risk register update output except which one?
A.
Probability of achieving time and cost estimates
B.
Priority list of risks
C.
Watch list of low-priority risks
D.
Risks grouped by categories
Explanation:
Probability of achieving time and cost estimates is an update that is produced from the
Quantitative risk analysis process. In Qualitative risk analysis probability of occurrence of a
specific risk is identified but not of achieving time and cost estimates.