You are the project manager of GHT project. A risk event has occurred in your project and you
have identified it. Which of the following tasks you would do in reaction to risk event occurrence?
Each correct answer represents a part of the solution. Choose three.
A.
Monitor risk
B.
Maintain and initiate incident response plans
C.
Update risk register
D.
Communicate lessons learned from risk events
Explanation:
When the risk events occur then following tasks have to done to react to it:
Maintain incident response plans
Monitor risk
Initiate incident response
Communicate lessons learned from risk events
Answer C is incorrect. Risk register is updated after applying appropriate risk response and at the
time of risk event occurrence.