You are the program manager for your organization and you are working with Alice, a project
manager in her program. Alice calls you and insists you to add a change to program scope. You
agree for that the change. What must Alice do to move forward with her change request?
A.
Add the change to the program scope herself, as she is a project manager
B.
Create a change request charter justifying the change request
C.
Document the change request in a change request form.
D.
Add the change request to the scope and complete integrated change control
Explanation:
Change requests must be documented to be considered. Alice should create a change request
form and follow the procedures of the change control system.