In the modified Waterfall Model:

In the modified Waterfall Model:

In the modified Waterfall Model:

A.
Product verification and validation are not included.

B.
The model was reinterpreted to have phases begin at project milestones.

C.
The model was reinterpreted to have phases end at project milestones.

D.
Unlimited backward iteration is permitted.

Explanation:
The modified Waterfall model was reinterpreted to have phases end at project milestones. Answer
“Unlimited backward iteration is permitted” is false because unlimited backward iteration is not
permitted in the modified Waterfall model. Answer “The model was reinterpreted to have phases
begin at project milestones” is a distracter. Answer “Product verification and validation are not
included” is false because verification and validation are included.