You work as a project manager for Bluewell Inc. You have identified a project risk. You have then
implemented the risk action plan and it turn out to be non-effective. What type of plan you should
implement in such case?
A.
Risk mitigation
B.
Risk fallback plan
C.
Risk avoidance
D.
Risk response plan
Explanation:
A risk fallback plan is a proper plan devised to identify definite action to be taken if the risk action
plan (Risk Mitigation Plan) is not helpful. Fallback plan is important in Risk Response Planning. If
the contingency plan for a risk is not successful, then the project team implements the fallback
plan. Fall-back planning is intended for a known and specific activity that may perhaps fail to
produce desired outcome. It is related with technical procedures and with the responsibility of the
technical lead.
described scenario, risk action plan is not turned to be effective, these should not be implemented
again.