What you should do in order to fulfill that?

You are the project manager of GHT project. You have implemented an automated tool to analyze
and report on access control logs based on severity. This tool generates excessively large
amounts of results. You perform a risk assessment and decide to configure the monitoring tool to
report only when the alerts are marked “critical”. What you should do in order to fulfill that?

You are the project manager of GHT project. You have implemented an automated tool to analyze
and report on access control logs based on severity. This tool generates excessively large
amounts of results. You perform a risk assessment and decide to configure the monitoring tool to
report only when the alerts are marked “critical”. What you should do in order to fulfill that?

A.
Apply risk response

B.
Optimize Key Risk Indicator

C.
Update risk register

D.
Perform quantitative risk analysis

Explanation:

As the sensitivity of the monitoring tool has to be changed, therefore it requires optimization of Key
Risk Indicator. The monitoring tool which is giving alerts is itself acting as a risk indicator. Hence to
change the sensitivity of the monitoring tool to give alert only for critical situations requires
optimization of the KRI.
the monitoring tools.



Leave a Reply 0

Your email address will not be published. Required fields are marked *