Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in
the project planning processes is now coming into fruition. What individual should respond to the
risk with the preplanned risk response
A.
Project sponsor
B.
Risk owner
C.
Diane
D.
Subject matter expert