The ____________ is the risk that remains after the implementation of new or enhanced controls

Fill in the blank with the appropriate phrase. The ____________ is the risk that remains after the
implementation of new or enhanced controls.

Fill in the blank with the appropriate phrase. The ____________ is the risk that remains after the
implementation of new or enhanced controls.

Answer: residual risk

Explanation:
residual risk