Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete
part of the project work for Eric’s organization. Due to a change request the ZAS Corporation is no
longer needed on the project even though they have completed nearly all of the project work. Is
Eric’s organization liable to pay the ZAS Corporation for the work they have completed so far on
the project?
A.
Yes, the ZAS Corporation did not choose to terminate the contract work.
B.
It depends on what the outcome of a lawsuit will determine.
C.
It dependson what the termination clause of the contract stipulates.
D.
No, the ZAS Corporation did not complete all of the work.