What is the likely outcome of creating this type of chart?

Your project has several risks that may cause serious financial impact should they happen. You
have studied the risk events and made some potential risk responses for the risk events but
management wants you to do more. They’d like for you to create some type of a chart that
identified the risk probability and impact with a financial amount for each risk event. What is the
likely outcome of creating this type of chart?

Your project has several risks that may cause serious financial impact should they happen. You
have studied the risk events and made some potential risk responses for the risk events but
management wants you to do more. They’d like for you to create some type of a chart that
identified the risk probability and impact with a financial amount for each risk event. What is the
likely outcome of creating this type of chart?

A.
Quantitative analysis

B.
Contingency reserve

C.
Risk response

D.
Risk response plan