You are the program manager for your project. You are working with the project managers
regarding the procurement processes for their projects. You have ruled out one particular contract
type because it is considered too risky for the program. Which one of the following contract types
is usually considered to be the most dangerous for the buyer?
A.
Cost plus incentive fee
B.
Fixed fee
C.
Cost plus percentage of costs
D.
Time and materials