which is calculated as a percentage of the initial estimated project costs?

In which of the following contract types, the seller is reimbursed for all allowable costs for
performing the contract work and receives a fixed fee payment which is calculated as a
percentage of the initial estimated project costs?

In which of the following contract types, the seller is reimbursed for all allowable costs for
performing the contract work and receives a fixed fee payment which is calculated as a
percentage of the initial estimated project costs?

A.
Firm Fixed Price Contracts

B.
Cost Plus Fixed Fee Contracts

C.
Fixed Price Incentive Fee Contracts

D.
Cost Plus Incentive Fee Contracts