What will be the Single Loss Expectancy of the project?

Mark is the project manager of the NHQ project in Spartech Inc. The project has an asset valued
at $195,000 and is subjected to an exposure factor of 35 percent. What will be the Single Loss
Expectancy of the project?

Mark is the project manager of the NHQ project in Spartech Inc. The project has an asset valued
at $195,000 and is subjected to an exposure factor of 35 percent. What will be the Single Loss
Expectancy of the project?

A.
$92,600

B.
$67,250

C.
$68,250

D.
$72,650