When developing a disaster recovery plan, which of the following is the third step?

When developing a disaster recovery plan, which of the following is the third
step?

When developing a disaster recovery plan, which of the following is the third step?

A.
Conduct the business impact analysis

B.
Develop recovery strategies

C.
Identify preventive controls

D.
Develop the contingency plan

Explanation:
The proper steps for developing a disaster recovery plan are laid out below;
. Develop the continuity planning policy statement.
. Conduct the business impact analysis (BIA).
. Identify preventive controls.
. Develop recovery strategies.
. Develop the contingency plan.
. Test the plan and conduct training and exercises.
. Maintain the plan.



Leave a Reply 1

Your email address will not be published. Required fields are marked *


Joe

Joe

7 Steps:
. Develop the policy.
. Conduct BIA(BIA).
. Preventive controls.
. Recovery
. Contingency plan.
. Test the plan
. Maintain the plan