You are the project manager of GHT project. You have initiated the project and conducted the
feasibility study. What result would you get after conducting feasibility study?
Each correct answer represents a complete solution. Choose all that apply.
A.
Recommend alternatives and course of action
B.
Risk response plan
C.
Project management plan
D.
Results of criteria analyzed, like costs, benefits, risk, resources required and organizational
impact
Explanation:
The completed feasibility study results should include a cost/benefit analysis report that:
Provides the results of criteria analyzed (e.g., costs, benefits, risk, resources required and
organizational impact)Recommends one of the alternatives and a course of action
plan project management and plan risk response, respectively. They are not the result of feasibility
study.