What also should the project manager update based on these scope changes?

Your project change control board has approved several scope changes that will drastically alter
your project plan. You and the project team set about updating the project scope, the WBS, the
WBS dictionary, the activity list, and the project network diagram. There are also some changes
caused to the project risks, communication, and vendors. What also should the project manager
update based on these scope changes?

Your project change control board has approved several scope changes that will drastically alter
your project plan. You and the project team set about updating the project scope, the WBS, the
WBS dictionary, the activity list, and the project network diagram. There are also some changes
caused to the project risks, communication, and vendors. What also should the project manager
update based on these scope changes?

A.
Stakeholder identification

B.
Vendor selection process

C.
Quality baseline

D.
Process improvement plan

Explanation:

When changes enter the project scope, the quality baseline is also updated. The quality baseline
records the quality objectives of the project and is based on the project requirements.
Answer D is incorrect. The process improvement plan aims to improve the project’s processes
regardless of scope changes.
Answer B is incorrect. The vendor selection process likely will not change because of added
scope changes. The vendors in the project may, but the selection process will not.
Answer A is incorrect. The stakeholder identification process will not change because of scope
additions. The number of stakeholders may change but how they are identified will not be affected
by the scope addition.