If there are automated tools for risk analysis, why does it take so much time to complete?
A.
A lot of data has to be gathered to be inputted into the automated tool.
B.
Management has to approve it and then a team has to be built.
C.
Risk analysis cannot be automated because of the nature of the assessment.
D.
Many people have to agree on the same data.
Explanation:
An analysis usually takes a long time to complete because of all the
data that must be properly gathered. There are usually a lot of different sources
for this type of data and properly extracting it is extremely time consuming. In
most situations, it involves setting up meetings with specific personnel and going
through a question and answer process.