What is the danger of not doing this?

Sam and David have not carried out proper project sizing and they are halfway through their risk analysis. What is the danger of not doing this?

Sam and David have not carried out proper project sizing and they are halfway through their risk analysis. What is the danger of not doing this?

A.
This step outlines the steps of mapping regulations and laws to an organization�s risk profile. The team will not be able to assess if the correct level of risk acceptance has been applied.

B.
The team will not know if they have secured funding for this project and may put the company into debt.

C.
The right team members have not been gathered for the risk analysis project and the team must start all over.

D.
The scope of the project is not defined, so the project may run out of money and still not meet its objectives.

Explanation:
When the scope of a project is not well defined, the project may run
out of money and still not meet its objectives.