Which of thefollowing lists these phases in the correct order?

Project management for software development has several phases. Which of thefollowing lists these phases in the correct order?

Project management for software development has several phases. Which of thefollowing lists these phases in the correct order?

A.
Project initiation, system design specifications, functional design analysis andplanning, software development, installation/implementation,operational/maintenance, disposal

B.
Project initiation, functional design analysis and planning, system design specifications, software development, installation/implementation,operational/maintenance, disposal

C.
Project initiation, functional design analysis and planning, software development, system design specifications, installation/implementation,operational/maintenance, disposal

D.
Project initiation, system design specifications, functional design analysis and planning, software development, operational/maintenance,installation/implementation, disposal

Explanation:
Software development project management should take place in thefollowing phases;

1. Project initiation
2. Functional design analysis and planning
3. System design specifications
4. Software development
5. Installation/implementation
6. Operational/maintenance
7. Disposal