Which of the following describes a parallel test?

Which of the following describes a parallel test?

Which of the following describes a parallel test?

A.
It is performed to ensure that some systems will run at the alternate site.

B.
All departments receive a copy of the disaster recovery plan and walk-through.

C.
Representatives from each department come together and go through the test collectively.

D.
Normal operations are shutdown.

Explanation:
In a parallel test, some systems are run at the alternate site and
results are compared with how processing takes place at the primary site. This is to
ensure the systems work in that area and productivity is not affected. This also
extends the previous test and allows the team to walk through the steps of setting
up and configuring systems at the off-site facility.